The Toronto Power Solutions Cogeneration – Etobicoke project will be subject to an extensive environmental screening process that includes:
  • Examining project’s potential impacts on the environment (land, air, water & noise)
  • Developing suitable measures to mitigate potential impacts
  • Consultations with all affected stakeholders
If the project is awarded an Ontario Power Authority contract detailed design of the project will commence April 2009. Subsequently would begin late 2009 and would be operational by early 2011.
Initial Community Open House 09/2008
Preliminary Design of Project 11/2008
Additional Community Open Houses (optional) 11/2008
Begin Environmental Screening Report 11/2008
Deadline to Submit Bid to Ontario Power Authority 12/2008
Complete Environmental Screening Report 12/2008
Submit Applications for Environmental Approvals Dec. 2008 & Permits 12/2008
Ontario Power Authority Contract Approval 02/2009